Duchesne Municipal Airport Design kicked off in May 2023 and was presented to the Duchesne City in June 2023 for review and approval. Base Bid Schedule work included, crack repair, pavement marking removal, application of an emulsified asphalt seal coat (satisfying FAA’s P-608 Specification) and reapplication of pavement markings on approximately 45,600 SY of airport pavements including Runway 17/35, and associated connectors and Apron. Because the base bid included application of P-608 seal coat to the runway, a runway friction test was required and completed. The project construction limits were entirely contained within the Airport’s existing property boundaries. No nonstandard conditions were addressed with this project. Construction Bid: $173,980 LOCAL PROJECTS 31